Interstate 5 Carpool and Mixed Flow Lane from Orange County Line to Interstate 605

Description: Orange County Line to Interstate 605 Junction. Widen Route 5 with HOV and Mixed flow lanes in various cities from .02 mi south of Artesia Avenue to .02 mi north of Florence Ave Overcrossing. (T

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Downey, La Mirada, Norwalk, Santa Fe Springs
Zip Code 90241, 90638, 90650, 90670
 
Senate District
30
Assembly District 56, 60
Congressional District 38, 39
 
Caltrans District
07
 
 
County/State Route Los Angeles 5
Postmile Begin/End 0.1 6.8
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  32705      
Lane Miles Added (HOV)  13    1.8  
Lane Miles Added (Mixed)  26    1.8  
Peak Period Time Savings (minutes)  2387480      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Syed Huq 213-897-6714   syed.huq@dot.ca.gov
Design (PS&E) Phase
Caltrans Syed Huq 213-897-6714   syed.huq@dot.ca.gov
Right of Way Phase
Caltrans Syed Huq 213-897-6714   syed.huq@dot.ca.gov
Construction Phase
Caltrans Syed Huq 213-897-6714   syed.huq@dot.ca.gov
 
Corridor System Management Plan
Caltrans Syed Huq 213-897-6714   syed.huq@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$387,000 $-71,989 $315,011
Non-bond Funding
State/Federal*
$382,730 $265,796 $648,526
Local**
$385,555 $134,519 $520,074
Non Budgeted ETC
$0 $0 $0
 
Total**** $1,155,285 $328,326 $1,483,611

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$7,523 $11,439 $18,962 $11,771
Design(PS&E)
$24,965 $70,565 $95,530 $56,255
Right of Way
$512,754 $139,886 $652,640 $242,953
Construction
$610,043 $106,436 $716,479 $485,748
 
Total* $1,155,285 $328,326 $1,483,611 $796,726

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
10/23/2001 

06/29/2007 
 

 
10/23/2001 

06/29/2007 
100  10/23/2001 

06/29/2007 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/1997 

06/30/2011 
 

 
01/01/1997 

06/30/2011 
100  01/02/2008 

06/30/2011 
-134 

Begin Right of Way Phase

End Right of Way Phase
09/03/2009 

05/10/2011 
 

04/20/2018 
09/03/2009 

12/20/2011 
100  09/03/2009 

12/20/2011 


Begin Construction Phase

End Construction Phase
12/30/2011 

04/29/2015 
 

04/20/2018 
11/28/2011 

05/27/2016 
11/28/2011 

05/19/2016 


Begin Closeout Phase

End Closeout Phase
06/03/2015 

09/26/2017 
 

 
07/05/2016 

07/02/2020 
100  07/05/2016 

04/02/2020 


Corridor System Management Plan
Adoption Date        
Implementation Date        
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 32705
Lane Miles Added (HOV) 13 1.8
Lane Miles Added (Mixed) 26 1.8
Peak Period Time Savings (minutes) 2387480

Bond Funding Cost
Adopted:
$387,000,000
Current Approved:
$51,983,000
Actual Expenditures:
$50,937,000

 

Status as of December 31, 2023.