Interstate 5 Carpool and Mixed Flow Lane from Orange County Line to Interstate 605 |
Description: Orange County Line to Interstate 605 Junction. Widen Route 5 with HOV and Mixed flow lanes in various cities from .02 mi south of Artesia Avenue to .02 mi north of Florence Ave Overcrossing. (T
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles |
City | Downey, La Mirada, Norwalk, Santa Fe Springs |
Zip Code | 90241, 90638, 90650, 90670 |
Senate District |
30 |
Assembly District | 56, 60 |
Congressional District | 38, 39 |
Caltrans District |
07 |
County/State Route | Los Angeles 5 |
Postmile Begin/End | 0.1 6.8 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 32705 | |
Lane Miles Added (HOV) | 13 | 1.8 |
Lane Miles Added (Mixed) | 26 | 1.8 |
Peak Period Time Savings (minutes) | 2387480 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Syed Huq | 213-897-6714 | syed.huq@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Syed Huq | 213-897-6714 | syed.huq@dot.ca.gov | |
Right of Way Phase |
Caltrans | Syed Huq | 213-897-6714 | syed.huq@dot.ca.gov | |
Construction Phase |
Caltrans | Syed Huq | 213-897-6714 | syed.huq@dot.ca.gov | |
Corridor System Management Plan |
Caltrans | Syed Huq | 213-897-6714 | syed.huq@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
CMIA |
$387,000 | $-71,989 | $315,011 | ||||
Non-bond Funding | |||||||
State/Federal* |
$382,730 | $265,796 | $648,526 | ||||
Local** |
$385,555 | $134,519 | $520,074 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $1,155,285 | $328,326 | $1,483,611 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$7,523 | $11,439 | $18,962 | $11,771 | |||
Design(PS&E) |
$24,965 | $70,565 | $95,530 | $56,255 | |||
Right of Way |
$512,754 | $139,886 | $652,640 | $242,953 | |||
Construction |
$610,043 | $106,436 | $716,479 | $485,748 | |||
Total* | $1,155,285 | $328,326 | $1,483,611 | $796,726 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
10/23/2001 06/29/2007 |
|
10/23/2001 06/29/2007 |
100 | 10/23/2001 06/29/2007 |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/1997 06/30/2011 |
|
01/01/1997 06/30/2011 |
100 | 01/02/2008 06/30/2011 |
-134 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
09/03/2009 05/10/2011 |
04/20/2018 |
09/03/2009 12/20/2011 |
100 | 09/03/2009 12/20/2011 |
0 0 |
|
Begin Construction Phase
End Construction Phase |
12/30/2011 04/29/2015 |
04/20/2018 |
11/28/2011 05/27/2016 |
0 | 11/28/2011 05/19/2016 |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
06/03/2015 09/26/2017 |
|
07/05/2016 07/02/2020 |
100 | 07/05/2016 04/02/2020 |
0 3 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 0 | 0 | |||||
Implementation Date | 0 | 0 |
????????
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 32705 | |
Lane Miles Added (HOV) | 13 | 1.8 |
Lane Miles Added (Mixed) | 26 | 1.8 |
Peak Period Time Savings (minutes) | 2387480 |
Bond Funding Cost | |
---|---|
Adopted: |
$387,000,000 |
Current Approved: |
$51,983,000 |
Actual Expenditures: |
$50,937,000 |
Status as of December 31, 2023.